
Short answer
A carrier’s liability is not unlimited. In carriage of goods by sea the carrier is not liable beyond 666.67 SDR per package or unit or 2 SDR per kilogramme of the gross weight of the goods lost or damaged; the two figures are calculated separately and whichever is higher applies (Article 1186/1 of the Turkish Commercial Code, “TCC”).
The limit is not an amount payable — it is a ceiling. If the actual loss falls below it, the actual loss is awarded. The date on which SDR is converted into Turkish Lira differs from regime to regime: the day of actual payment at sea, the date of delivery to the carrier for domestic road carriage, and the date of judgment under CMR and Montreal. That single difference can double or halve the recovery.
The limit is not absolute: a carrier who caused the loss intentionally or recklessly and with knowledge that loss would probably result cannot rely on it (TCC Article 1187). In air cargo the position is the reverse — there the limit stands even in cases of gross fault.
Contents
- Why doesn’t the carrier pay the whole loss?
- Which limit applies to which mode of carriage?
- How is the sea limit calculated: 666.67 SDR or 2 SDR?
- Where and when is the value of the goods assessed?
- Is a container one package, or is each carton inside it separate?
- What does the carrier pay for delay: what is the 2.5 times freight cap?
- When does limitation fall away altogether?
- Can the parties change the limit by contract?
- Can the shipowner limit globally by tonnage? (LLMC)
- How do the SDR regimes compare across modes?
- How do the courts apply the 8.33 SDR road limit?
- Is the air cargo limit still 19 or 22 SDR?
- Which date governs the SDR exchange rate?
- How many days do you have to give notice of damage?
- How long do you have to bring the claim?
- Which documents must be gathered before filing?
- Frequently asked questions
- Why running these files correctly matters
Why doesn’t the carrier pay the whole loss?
When cargo arrives damaged and the invoice figure is on the table, cargo interests naturally expect full recovery. Transport law does not work that way. A carrier’s liability for loss of, damage to or delay in delivery of the goods is not, as a rule, unlimited: it is subject to ceilings expressed in Special Drawing Rights (SDR) under both domestic and international instruments.
Court of Cassation, 11th Civil Chamber, 29.11.2016, File 2015/11896, Decision 2016/9213: the Chamber held that the carrier’s liability under those provisions is not unlimited, and that the governing principle is that the carrier is liable in a limited manner and not beyond the actual loss, while if the actual loss exceeds the limitation figure laid down in those provisions the carrier is liable up to the limitation figure.
11th Civil Chamber, 16.02.2016, File 2015/4339, Decision 2016/1537: the Chamber repeated that there is no unlimited liability in the carriage of goods.
Two consequences follow. First, the limit is a ceiling, not a payment: if the actual loss is below it, the actual loss is awarded. Second, the ceiling is a calculable figure and must be calculated before proceedings are issued — otherwise court fees are paid on a sum that will never be recovered.
Which limit applies to which mode of carriage?
The general regime for contracts of carriage of goods and the maritime regime differ materially in their unit of account, ceilings and conversion dates.
- General carriage of goods (road): under Article 882 TCC the limit is 8.33 SDR per kilogramme of the gross weight of the consignment.
- Carriage of goods by sea (contracts of affreightment): Article 1186 TCC lays down a dual limit — 666.67 SDR per package or unit, or 2 SDR per kilogramme of gross weight.
- Global limitation in maritime trade: by reference in Articles 1328 and 1329 TCC, the 1976 Convention on Limitation of Liability for Maritime Claims (LLMC) and its 1996 Protocol allow a global limitation based on the ship’s tonnage, and they apply even where the dispute has no foreign element.
Article 1186 TCC mirrors the liability ceilings familiar from the Hague/Visby Rules, which makes the Turkish framework recognisable to foreign parties and their P&I clubs.
How is the sea limit calculated: 666.67 SDR or 2 SDR?
Article 1186/1 TCC provides:
“The carrier shall in no event be liable for loss or damage to, or in connection with, the goods in an amount exceeding 666.67 Special Drawing Rights per package or unit, or two Special Drawing Rights per kilogramme of gross weight of the goods lost or damaged, whichever is the higher, unless the nature and value of the goods have been declared by the shipper before shipment and inserted in the sea waybill. The Special Drawing Right shall be converted into Turkish Lira according to the value determined by the Central Bank of the Republic of Türkiye on the day of actual payment or on such other date as the parties may agree.” (unofficial translation)
The calculation runs in four steps:
- Package/unit calculation: the number of packages or units lost or damaged is multiplied by 666.67 SDR.
- Weight calculation: the gross weight in kilogrammes of the goods lost or damaged is multiplied by 2 SDR.
- The applicable ceiling: the two figures are compared and the higher one is taken as the limit — that is, the figure more favourable to the claimant.
- Conversion: unlike general carriage, where the date of delivery governs, the SDR rate is the Central Bank rate on the day of actual payment (or such other date as agreed).
In practice, heavy cargo in few packages produces a higher figure on the weight basis, while light cargo in many packages produces a higher figure on the package basis. The value of a claim cannot be assessed without running both.
Cargo damaged and the carrier is invoking limitation?
The ceiling calculation, the bill of lading particulars and the notice deadlines decide these cases. Let us review your documents with you.
Where and when is the value of the goods assessed?
Article 1186/2 TCC provides that the total compensation payable by the carrier is calculated by reference to the value of the goods at the place and on the day at which they were, or should have been, discharged from the ship in accordance with the contract of affreightment. The value is fixed according to the commodity exchange price, or, if there is no such price, according to the current market price, or, in the absence of both, by reference to the normal value of goods of the same nature and quality.
So the court first establishes the actual loss at the place and date of discharge. If that figure is below the statutory ceiling, the actual loss is awarded; if it exceeds the ceiling, the limitation figure under Article 1186/1 applies. The commercial invoice alone is not decisive.
Is a container one package, or is each carton inside it separate?
This is the single technical point that moves the figure most in maritime cargo claims. Article 1186/3 TCC provides that where goods are consolidated in a container, pallet or similar article of transport, each package or unit enumerated in the sea waybill as packed in that article of transport is deemed a separate package or unit; otherwise the article of transport itself is deemed a single package or unit. Where the article of transport is itself lost or damaged it counts as a separate package, unless it is owned or supplied by the carrier.
If the bill of lading enumerates the cartons inside the container, the 666.67 SDR calculation runs on the number of cartons. If it does not, the whole container is one unit. In a container holding 500 cartons that distinction moves the ceiling between 666.67 SDR and 333,335 SDR — a difference no subsequent legal work can recover.
What does the carrier pay for delay: what is the 2.5 times freight cap?
Under Article 1186/6 and /7 TCC, the carrier’s liability for exceeding the period of carriage is limited to two and a half times the freight payable for the delayed goods, and that amount may not exceed the total freight payable under the contract of affreightment. Where paragraphs one and six apply together, the carrier’s aggregate liability may not exceed the amount for which it would be liable under paragraph one in case of total loss of the goods.
Commercial losses from delay are usually many times the freight; the ceiling nevertheless tracks the freight. Where delay also caused physical loss or damage, the loss-and-damage limits apply instead.
When does limitation fall away altogether?
Declaration of value and false declaration
Where the shipper declares the nature and value of the goods before shipment and has them inserted in the transport document, limitation does not apply. But Article 1186/5 TCC provides that if the shipper has knowingly misstated the nature or value of the goods, the carrier is not liable at all for loss of or damage to the goods. The provision cuts both ways: an accurate declaration removes the ceiling, a deliberate false declaration removes liability.
Intent or recklessness
Article 1187/1 and /2 TCC provide that where it is proved that the loss or the delay in delivery resulted from an act or omission of the carrier done with intent to cause such loss or delay, or recklessly and with knowledge that such loss or delay would probably result, the carrier cannot rely on the limits in Article 1186. The same applies to the carrier’s servants and agents, who cannot invoke those limits through Article 1190/2 either.
The threshold is high in practice. As the decisions below show, the courts preserve limitation in cases of ordinary negligence and require concrete evidence of intent or recklessness. Moreover, under Article 1190 TCC the defences and limits apply equally to claims brought against the carrier in tort — re-pleading the claim in tort is not a route around the ceiling.
Can the parties change the limit by contract?
Yes, upwards. Under Article 1186/8 TCC the parties may increase the limits by a clause in the contract of carriage, in which case the agreed figure becomes the limit. In practice carriers are also found to have waived limitation entirely:
Istanbul Regional Court of Appeal, 14th Civil Chamber, 19.10.2022, File 2022/1635, Decision 2022/1344: the Chamber first held that under Article 882/1(b) TCC only the weight of the damaged goods is to be taken into account in determining the ceiling, and calculated that at 8.33 SDR per kilogramme the defendant’s upper limit was 400,673 SDR; it then held that in the contract of carriage between the parties the carrier had waived its right to rely on limitation and that this clause was valid.
The decision shows that the contract wording matters as much as the ceiling. On high-value shipments, an ad valorem declaration against additional freight, or a waiver clause, changes the value of the claim completely.
Can the shipowner limit globally by tonnage? (LLMC)
Alongside package limitation, maritime law allows global limitation by reference to the ship’s tonnage. Article 1328/1 TCC provides that liability arising from maritime claims may be limited in accordance with the 1976 Convention on Limitation of Liability for Maritime Claims, published in the Official Gazette of 4 June 1980 No. 17007, and the Protocol of 2 May 1996 amending it, or such international conventions as may replace them and be accepted by the Republic of Türkiye. Article 1329 TCC extends that rule to disputes with no foreign element within the meaning of Article 1(1) of Law No. 5718 on Private International Law and Procedure.
The limits rose in 2015 — do not use the old table
The limits under the 1996 Protocol were increased by roughly 51% by the IMO Legal Committee in 2012 (Resolution LEG.5(99)), and the new figures took effect on 8 June 2015:
| Type of claim | Ships up to 2,000 GT | Additional tonnage bands |
|---|---|---|
| Loss of life or personal injury | 3.02 million SDR (previously 2 million SDR) | 1,208 SDR per ton from 2,001 to 30,000 tons · 906 SDR from 30,001 to 70,000 tons · 604 SDR above 70,000 tons |
| Other claims (property, delay, pollution and the like) | 1.51 million SDR (previously 1 million SDR) | 604 SDR per ton from 2,001 to 30,000 tons · 453 SDR from 30,001 to 70,000 tons · 302 SDR above 70,000 tons |
The Turkish maritime administration circulated the amendment and required P&I cover for ships calling at or leaving port facilities in Turkish maritime jurisdiction to match the new limits. A fund calculation based on the pre-2015 table is simply wrong today.
An example from practice
Istanbul Regional Court of Appeal, 12th Civil Chamber, 12.11.2025, File 2025/1642, Decision 2025/1831: following a fire on board, the defendant argued that its liability was limited to the amount calculated under Article 6(1)(b) of the 1976 London Convention, namely 3,907,800 units of account (SDR), and that converted at the rate current at the date of the casualty (1 SDR = 1.8761) the ceiling for all loss arising from the burning of every vehicle and cargo on board was 7,331,423.58; it further relied on clause 19 on the reverse of the bill of lading limiting liability per unit.
The court dismissed the claim, holding that since a final judgment concerning the same fire had established that there was no fault on the part of the shipowner, and no evidence in the file warranted a different conclusion, the dismissal was not erroneous.
The decision is instructive because it shows that in major casualties proof of fault is more decisive than the limitation fund itself.
How do the SDR regimes compare across modes?
| Mode | Legal basis | SDR ceiling | Date governing the SDR rate | Loss of the right to limit |
|---|---|---|---|---|
| Sea | TCC Articles 1186, 1187 | 666.67 SDR per package or 2 SDR per kg gross, whichever is higher | Day of actual payment (or as agreed) | Loss caused intentionally or recklessly (TCC Art. 1187) |
| Road (domestic) | TCC Articles 882, 886 | 8.33 SDR per kg of gross weight | Date the goods were handed to the carrier (or as agreed) | Loss caused intentionally or recklessly (TCC Art. 886) |
| Road (international) | CMR Articles 23, 29 | 8.33 SDR per kg of gross weight short | Rate at the date of judgment (or as agreed) | Wilful misconduct or equivalent default (CMR Art. 29) |
| Air (cargo) | Montreal Convention Article 22 | 26 SDR per kg from 28 December 2024 (previously 19 and 22 SDR) | Rate at the date of judgment | Limitation in cargo carriage is absolute; it cannot be broken even for gross fault |
Four rows mean four different calculations. On a multimodal shipment the sea leg and the road leg are subject to different ceilings, so establishing at which stage the damage occurred directly determines the recovery.
How do the courts apply the 8.33 SDR road limit?
Domestic carriage (TCC Articles 882 and 886)
Istanbul 10th Commercial Court, 04.06.2024, File 2022/614, Decision 2024/429: the court emphasised that the carrier’s liability is limited to 8.33 SDR per kilogramme of the gross weight of the consignment and that the SDR is converted at the Central Bank rate on the date the goods were handed to the carrier or such other date as agreed; it added that compensation for total or partial loss is calculated by reference to the value of the goods at the place and time at which they were taken over, and arrived at a total of 109.48 by adding the freight recoverable under Article 883(1). Since no intent was established, it held that full compensation under Article 886 did not arise.
Antalya Regional Court of Appeal, 11th Civil Chamber, 16.09.2025, File 2022/1036, Decision 2025/743: the Chamber restated the 8.33 SDR rule and stressed that under Article 886 TCC a carrier, or the persons referred to in Article 879, proved to have caused the loss intentionally or recklessly and with knowledge that such loss would probably result cannot benefit from the limits.
Istanbul Regional Court of Appeal, 14th Civil Chamber, 24.10.2024, File 2021/1428, Decision 2024/1498: having taken the SDR rate closest to the date of judgment (1 SDR = 45.4959 on 23 October 2024) and calculated 1008.33 x 45.4959 = 37,898.08, the Chamber added that the figure found is not the amount of liability but the carrier’s maximum limit, and that the defendant is liable, up to that limit, for the portion of the actual loss corresponding to its own fault. It found no basis for applying Article 886.
Istanbul Regional Court of Appeal, 43rd Civil Chamber, 20.11.2023, File 2020/1807, Decision 2023/1233: the Chamber confirmed both the 8.33 SDR ceiling and the conversion rule tied to the date the goods were handed over, and relied on Article 886 TCC as the route by which the limit is lost.
Istanbul Anadolu 11th Commercial Court, 09.05.2025, File 2024/39, Decision 2025/414: the court summarised that in damaged deliveries the carrier’s liability is limited to 8.33 SDR per kilogramme of the gross weight attributable to the damaged part, and that the lower of the loss value and the SDR calculation governs; it found that the conditions of Article 886 were not met.
Istanbul 8th Commercial Court, 26.03.2025, File 2023/224, Decision 2025/212: the court applied the Article 882 limits and allowed the claim in part, noting that no evidence showed the three severely damaged packages had been damaged intentionally or recklessly, so full compensation under Article 886 did not arise.
Istanbul Regional Court of Appeal, 13th Civil Chamber, 02.05.2025, File 2022/1952, Decision 2025/721: the Chamber noted that, unlike the former Code, the present TCC limits the carrier’s liability in line with the international conventions, and that compensation is capped at 8.33 SDR per kilogramme of the gross weight of the goods lost or of the part that lost value.
International carriage under CMR
Istanbul Anadolu 4th Commercial Court, 10.10.2024, File 2022/518, Decision 2024/742: the ceiling was calculated under CMR Article 23(3) as 470.01 kg x 8.33 SDR = 3,915.18 SDR, the court stressing that the carrier’s liability cannot exceed 8.33 units of account per kilogramme of the gross weight of the damaged goods.
Bakırköy 7th Commercial Court, 11.02.2025, File 2024/448, Decision 2025/137: the court held that the dispute fell to be resolved primarily under CMR, that there was no room to apply Article 29 against the defendant carrier, which could therefore rely on limitation, and — applying Article 23(7), under which the amounts are converted at the rate current at the date of judgment or as agreed — fixed the ceiling at 13,328.00 SDR.
Court of Cassation, 11th Civil Chamber, 20.03.2017, File 2016/908, Decision 2017/1652: compensation for total or partial loss under CMR Article 23 is calculated by reference to the value of the goods at the place and time at which they were accepted for carriage, established by commodity exchange price, failing that by current market price, and failing both by the normal value of goods of the same kind and quality; liability nevertheless cannot exceed 8.33 units of account per kilogramme of gross weight short.
Court of Cassation, 11th Civil Chamber, 29.11.2016: the exceptions to limitation were identified as a declared value exceeding the limit entered in the consignment note against a surcharge, and wilful misconduct or default equivalent to wilful misconduct under Article 29.
Istanbul 15th Commercial Court, 26.06.2024, File 2023/178, Decision 2024/378: with the damaged goods recorded at 3.01 kg, the court calculated 3.01 kg x 8.33 SDR = 25.0733 SDR and converted it at the Central Bank SDR/TRY rate closest to the date of judgment, allowing the claim in part.
Is the air cargo limit still 19 or 22 SDR?
Note: the cargo limit is 26 SDR from 28 December 2024
The five-yearly review mechanism in Article 24 of the Montreal Convention was applied; ICAO’s 2024 review put the inflation factor at 17.9% and the limits were revised with effect from 28 December 2024. The cargo limit in Article 22(3) rose from 22 SDR to 26 SDR per kilogramme. The passenger death and injury limit became 151,880 SDR, passenger delay 6,303 SDR and baggage 1,519 SDR.
Calculations based on 19 or 22 SDR are therefore incomplete for carriage after 28 December 2024. The decisions below should be read with their dates in mind: each applied the limit in force at the time of the carriage before it.
Bakırköy 5th Commercial Court, 21.11.2022, File 2022/175, Decision 2022/1101: the court held that under Article 22(3), absent a declaration of special interest, liability for baggage and cargo is limited to 22 SDR per kilogramme of the gross weight lost or damaged; that liability equals the actual loss but is capped at the Article 22 figure; and that limitation in baggage or cargo carriage cannot become unlimited.
Istanbul Regional Court of Appeal, 12th Civil Chamber, 27.10.2022, File 2020/201, Decision 2022/1498: absent a special declaration made when the cargo was handed over, with a supplementary sum paid if required, liability was limited to 19 SDR per kilogramme as at the date of damage; where such a declaration is made, the carrier is liable up to the declared sum unless it proves that sum exceeds the consignor’s actual interest in delivery.
Istanbul 7th Commercial Court, 22.10.2025, File 2020/772, Decision 2025/765: applying Articles 22(3) and 24(1), the court calculated 224.5 kg x 22 = 4,939 SDR and, at the Central Bank rate closest to judgment (1 SDR = 1.363 USD), fixed the ceiling at USD 6,736.59; since the loss exceeded that figure, judgment was given up to the limit.
Istanbul 4th Commercial Court, 23.12.2025, File 2024/464, Decision 2025/931: the court noted that although Article 22(5) provides for the loss of limitation in respect of baggage and passengers, limitation in cargo carriage applies absolutely, and capped liability at 18 kg x 22 SDR = 396 SDR.
Istanbul 20th Commercial Court, 24.05.2023, File 2022/480, Decision 2023/419: the court accepted that under the Montreal regime limitation cannot be broken and applies even where the carrier is grossly at fault, found the carrier liable in ordinary fault rather than gross fault, and fixed compensation at 79.90 SDR.
Istanbul Regional Court of Appeal, 43rd Civil Chamber, 31.10.2024, File 2021/987, Decision 2024/1581 and 06.11.2025, File 2022/541, Decision 2025/1598: both decisions confirmed the 19 SDR limit and held that even where the loss of or damage to the cargo results from intentional or reckless conduct of the carrier or its servants, this does not prevent the carrier from relying on limitation under the Convention (the second citing the Court of Cassation, 11th Civil Chamber, 13.03.2014, File 2012/14200, Decision 2014/4905).
Istanbul Regional Court of Appeal, 43rd Civil Chamber, 28.11.2024, File 2021/1679, Decision 2024/1741: besides the cargo limit, the Chamber clarified the weight basis: under Article 22(4), where part of the cargo or any object contained in it is destroyed, lost or delayed, the weight to be taken into consideration is only the total weight of the package or packages concerned. On conversion, despite the date-of-judgment rule, the calculation at the date of damage was preserved given the appellant’s position.
Istanbul Regional Court of Appeal, 14th Civil Chamber, 19.02.2026, File 2022/1447, Decision 2026/284: liability under the Convention is limited as a rule, but where the consignor makes a special declaration of interest and pays a supplementary sum if required, the carrier answers for the actual loss; the chargeable weight of 155 kg used by the expert was upheld.
Istanbul 14th Commercial Court, 28.01.2026, File 2023/748, Decision 2026/79: the court explained the role of the freight forwarder, which assumes responsibility from collection to delivery, calculated 27.25 x 22 = 599.5 SDR and, at the SDR/USD rate on the report date, arrived at USD 821.35; as the net weight of the damaged goods was absent from the survey report, one package was treated as wholly damaged under Article 22(4).
Which date governs the SDR exchange rate?
Same loss, same ceiling, different conversion date — and a different outcome:
- Sea (Article 1186/1 TCC): the Central Bank rate on the day of actual payment, or such other date as agreed. The delivery-date rule applicable to road carriage does not apply at sea.
- Domestic road (Article 882/4 TCC): the date the goods were handed over to the carrier.
- CMR (Article 23/7): conversion into the national currency of the forum at the rate current at the date of judgment or as agreed between the parties.
- Montreal (Article 23): the rate at the date of judgment.
Given the depreciation of the Turkish Lira, this is not an academic distinction. In a long-running maritime case the “day of actual payment” rule works markedly in the claimant’s favour, while in a road case the handover-date rate pulls the ceiling down. The claim should therefore be pleaded in SDR, with the conversion date expressly stated.
Which is lower — the SDR ceiling or the actual loss?
We can work out the ceiling and the conversion date together for sea, road and air claims, so you see the real value of the file from the outset.
How many days do you have to give notice of damage?
This step comes before the ceiling calculation. Failure to give notice in time does not always destroy the claim, but it shifts the burden of proof in the carrier’s favour and seriously weakens the file.
| Regime | Apparent damage | Non-apparent damage | Delay | Consequence |
|---|---|---|---|---|
| Sea — TCC Art. 1185 | Written notice at the latest on delivery | Within 3 consecutive days of delivery | — | Presumption that the goods were delivered as described in the transport document and that any loss arose from a cause for which the carrier is not liable (rebuttable) |
| Road — TCC Art. 889 | At the latest on delivery | Within 7 days of delivery | Within 21 days of the date on which the goods should have been delivered | Shift of the burden of proof |
| CMR Art. 30 | On delivery | 7 days | 21 days | Presumption and evidential difficulty |
| Montreal Art. 31 | — | 14 days | 21 days | No action lies if notice is not given in time |
Under Article 1185/2 TCC no notice is required where the goods have been jointly surveyed by the court, a competent authority or officially appointed experts with the parties present. The safest course in practice is a delivery receipt claused at the moment of delivery together with a simultaneous call for a surveyor.
How long do you have to bring the claim?
- Sea: claims against the carrier are as a rule subject to a one-year limitation period, running from delivery of the goods or, in case of total loss, from the date on which they should have been delivered.
- Road (Article 855 TCC): one year as a rule; three years where the loss was caused intentionally or recklessly and with knowledge that it would probably result.
- CMR (Article 32): one year; three years in case of wilful misconduct or equivalent default.
- Montreal (Article 35): a two-year period of extinction which is not suspended or interrupted.
Because the starting point and the applicable regime depend on the transport documents, both should be verified separately in every file.
Which documents must be gathered before filing?
- Bill of lading / CMR consignment note / air waybill — in particular whether the number of cartons inside the container is enumerated
- Commercial invoice, packing list and gross/net weight breakdown (the ceiling cannot be calculated without them)
- Delivery receipt, clausing, container interchange report and seal records
- Survey report and photographs; ideally a joint survey with the parties present
- The contract of carriage and the reverse-side terms of the bill of lading — is there a waiver or an ad valorem declaration?
- Freight invoice (essential in delay claims, where the ceiling tracks the freight)
- Insurance policy and any subrogation documents
- Correspondence: the date of the damage notice and the person to whom it was addressed
Frequently asked questions
The carrier says its liability is capped in SDR. Is it still worth suing?
Usually yes. The cap is a ceiling: if your actual loss is below it, the whole loss is recoverable. And the ceiling itself may be far higher than the carrier suggests if the cartons are enumerated in the bill of lading, if the weight basis exceeds the package basis, or if the carrier has waived limitation.
Is the SDR calculation done even where the actual loss is below the cap?
It is done, but it does not change the result. The court first establishes the actual loss at the place and date of discharge; if that is below the ceiling, the actual loss is awarded. The ceiling bites only when the loss exceeds it.
What if the number of cartons in the container is not stated in the bill of lading?
Under Article 1186/3 TCC the container counts as a single package or unit. The package basis then stops at 666.67 SDR and the weight basis (2 SDR per kg) is usually the higher of the two — and the higher figure applies.
Can I escape limitation by suing in tort?
No. Under Article 1190 TCC the defences and limits of liability apply equally to claims brought against the carrier in tort for loss of, damage to or delay in delivery of the goods.
Does gross fault break the limit?
At sea and on the road the test is not gross fault but intent or recklessness with knowledge that loss would probably result (TCC Articles 1187 and 886; CMR Article 29). In air cargo the limit is absolute: the courts hold that it cannot be broken even for gross fault.
Has the air cargo limit really become 26 SDR?
Yes. Following ICAO’s five-yearly review the cargo limit rose from 22 to 26 SDR per kilogramme with effect from 28 December 2024. For earlier carriage the limit in force at the time — 19 or 22 SDR — applies.
My delay loss is many times the freight. Can I recover it in full?
Not at sea. The carrier’s liability for delay is limited to two and a half times the freight payable for the delayed goods and cannot exceed the total freight. If the delay also caused loss or damage, the loss-and-damage limits apply.
Is an ad valorem declaration worth the extra freight?
Where the nature and value are declared before shipment and inserted in the transport document, limitation does not apply. For high-value, low-weight cargo — electronics, spare parts, pharmaceuticals — the cost of declaring is usually small against the gap between the ceiling and the actual loss. But a knowingly false declaration removes the carrier’s liability altogether under Article 1186/5 TCC.
There was a fire on board and the owner has constituted a fund. What happens to my claim?
The shipowner may limit globally by tonnage under LLMC and the 1996 Protocol through Articles 1328 and 1329 TCC, in which case claimants share rateably in the fund. The limits rose by roughly 51% on 8 June 2015. Proof of fault tends to be decisive in these files.
Which regime applies to multimodal carriage?
As a rule, the regime governing the leg on which the damage occurred. Where that cannot be established, the contract terms and transport documents govern. Leg-by-leg delivery receipts and container interchange reports are therefore critical.
Why running these files correctly matters
Cargo claims turn on the correct calculation before they turn on legal argument. A handful of technical choices decide the outcome:
- Which regime applies (Article 882 or 1186 TCC, CMR or Montreal) moves the ceiling between 8.33 SDR and 666.67 SDR.
- Whether the container contents are enumerated in the bill of lading can move the ceiling by a factor of hundreds.
- Choosing the wrong conversion date turns a correctly calculated ceiling into an under-pleaded claim.
- Missing the notice deadline shifts the burden of proof to the carrier’s advantage.
- Limitation and extinction periods differ by regime; the two-year Montreal period is neither suspended nor interrupted.
- Unless intent or recklessness is supported by concrete evidence the ceiling stands, so building the claim on that allegation alone is a risky choice.
- Failing to plead the sum in SDR with the correct conversion date, or to reserve rights as to the excess, costs recovery.
Where these disputes concentrate in and around Istanbul
Cargo damage and carriage claims cluster along the port, shipyard and logistics corridors of Istanbul. On the Anatolian side the shipyards, warehouses and logistics facilities of Tuzla, Pendik, Kartal, Maltepe, Sultanbeyli and Beykoz; on the European side the Ambarlı belt with Avcılar, Beylikdüzü, Küçükçekmece, Zeytinburnu, Bakırköy and Başakşehir; and for air cargo the areas around Arnavutköy (Istanbul Airport) and Pendik (Sabiha Gökçen). In Kocaeli, the ports and organised industrial zones of Gebze, Dilovası, Çayırova, Darıca and Körfez account for a significant share of these files.
The type of dispute varies with the location: container terminals generate arguments about package enumeration and bill of lading particulars; bulk and project cargo about discharge method and stevedoring fault; air cargo about temperature chain and the number of packages. In all three, what decides the case is whether the damage was properly documented at the moment of delivery.
2M Hukuk Law Firm
Founder: Meryem Günay, Attorney at Law. The firm practises in maritime and transport law, ship arrest and maritime enforcement, commercial disputes, urban transformation and condominium law, immigration law and administrative litigation, handling files before the commercial courts on both the Anatolian and European sides of Istanbul and in the Kocaeli region.
Address: Postane Mahallesi, Seher Sokak No: 18/2, Tuzla / Istanbul, Türkiye
Phone: +90 505 390 25 48 | E-mail: info@2mhukuk.com
Sources and legislation
- Turkish Commercial Code No. 6102 — Articles 855, 879, 880-883, 886, 889, 1185, 1186, 1187, 1190, 1328, 1329 (mevzuat.gov.tr)
- 1976 Convention on Limitation of Liability for Maritime Claims (LLMC) and the Protocol of 2 May 1996; the 2012 amendments to the Protocol (IMO Legal Committee, Resolution LEG.5(99)), in force 8 June 2015
- CMR — Convention on the Contract for the International Carriage of Goods by Road, Articles 23, 29, 30, 32
- Montreal Convention 1999, Articles 22, 23, 24, 31, 35; revised limits following ICAO’s 2024 review, effective 28 December 2024
- Law No. 5718 on Private International Law and International Civil Procedure, Article 1
This article is provided for general information only and does not constitute legal advice. Every file must be assessed on its own documents and evidence. Statutory texts quoted here in English are unofficial translations. The current texts of the judgments cited should be verified through UYAP and the official case-law databases.


